Here's the latest information that the State Park has released regarding the new Middle Bass Marina.
* Lottery: An Update for those that have been following this
program
We had 35 applications received by the deadline of February 25,
2009, 5:00PM at the Catawba State Park Office. We have a total of 70
slips that were set aside for the seasonal dock lottery.
The drawing will be conducted at the Catawba State Park office
on March 5, 2009, 6:00 PM
* Spring 2009 Construction Plans:
It is hoped that by the end of March we will again be on the
island with construction continuing.
* Construction on the Water Tower and lines will continue
* The Electric infrastructure will be built out.
* New Roadways will be further planned and temporary roads will be
used.
* There are to be some finishing touches to the marina basin,
including 2 pipe piles and some rock in the channel to be cleared out.
* Docks are currently scheduled to be completed for public use the
beginning of June.